CTF Backup Operations Control Center Transformer Upgrades

Jaxson Point Electrical Construction was responsible for replacing seven high-voltage transformers at the CTF Backup Operations Control Center for WMATA. This critical project improved power reliability for WMATA’s essential operations.

Scope of Work:

The project involved the installation of seven new HV transformers, ensuring a stable and secure power supply for WMATA’s operations center.

Outcome:

The new transformers improved power stability for the Backup Operations Control Center, ensuring continued WMATA service.

Client:

  • Washington Metropolitan Area Transit Authority (WMATA)

General Contractor:

  • Potomac Construction

Budget:

  • $3.3 million

Project Highlights:

  • Power Infrastructure Upgrade: Ensured reliability for WMATA’s backup systems.

  • High-Voltage Expertise: Installed transformers safely and efficiently.